Artikel 23 Pipa Bawah Laut
Pipeline Hydro Test Pressure Determination
Hydrostatic testing has long been used to determine and verify
pipeline integrity. Several types of information can be obtained through
this verification process.
However, it is essential to identify the limits of the test process and obtainable results. There are several types of flaws that can be detected by hydrostatic testing, such as:
However, it is essential to identify the limits of the test process and obtainable results. There are several types of flaws that can be detected by hydrostatic testing, such as:
- Existing flaws in the material,
- Stress Corrosion Cracking (SCC) and actual mechanical properties of the pipe,
- Active corrosion cells, and
- Localized hard spots that may cause failure in the presence of hydrogen.
There are some other flaws that cannot be detected by hydrostatic
testing. For example, the sub-critical material flaws cannot be detected
by hydro testing, but the test has profound impact on the post test
behavior of these flaws.
Given that the test will play a significant role in the
nondestructive evaluation of pipeline, it is important to determine the
correct test pressure and then utilize that test pressure judiciously,
to get the desired results.
When a pipeline is designed to operate at a certain maximum operating
pressure (MOP), it must be tested to ensure that it is structurally
sound and can withstand the internal pressure before being put into
service. Generally, gas pipelines are hydrotested by filling the test
section of pipe with water and pumping the pressure up to a value that
is higher than maximum allowable operating pressure (MAOP) and holding
the pressure for a period of four to eight hours.
Test Pressure And Materials SMYS
Though codes
and regulatory directives are specific about setting test pressure to
below 72% or in some cases up to 80% of the SMYS of the material, there
is a strong argument on testing a constructed pipeline to “above 100% of
SMYS,” and as high as 120% of SMYS is also mentioned. Such views are
often driven by the desire to reduce the number of hydrotest sections,
which translates in reduction in cost of construction. In this context,
it is often noted that there is some confusion even among experienced
engineers on the use of term SMYS and MOP/MAOP in reference to the
hydrotest pressure.
It may be pointed out that the stress in material (test pressure) is
limited by the SMYS. This is the law of physics, and is not to be broken
for monetary gains at the peril of pipeline failure either immediate or
in the future.
In this regard, section 32 of directive No. 66 of the Alberta Energy
and Utilities Board in 2005 is of importance. The guidance is specific
about the situation. It directs that if the test pressure causes hoop
stress in the material exceeding 100% of the material SMYS, then the
calculation and the entire hydro test procedure needs to be submitted to
the board for review and approval.
Stress Relieving And Strength
Often there is argument presented that higher test pressures exceeding
100% of the SMYS will increase the “strength” of the material and will
“stress relieve” the material. Both arguments have no technical basis to
the point they are made. We will briefly discuss both these arguments
here:
- Higher test pressure will “increase the strength.” As the material is stressed beyond its yield point, the material is in plastic deformation stage, which is a ductile stage, and hence it is in the constant process of losing its ability to withstand any further stress. So, it is not increasing in strength but progressively losing its strength.
- The second argument of “stress reliving” is linked with the “increase the strength” argument. The stress relief of material is carried out to reduce the locked-in stresses. The process reorients the grains disturbed often by cold working or welding. The stress relief process effectively reduces the yield strength. Thus, it does not “strengthen” the material. Note: It may be pointed out that a limited relaxation of stresses does occur by hydro testing, but the test pressure should be less than the material’s yield point.
Another point to note here is that there is a stage in the stressing
of the material where strain hardening occurs and the material certainly
gains some (relative) hardness, and thereby, strength. This happens as
necking begins but, at that point, unit area stress is so low that the
strength of the material is lost and it remains of no practical use,
especially in context with the pipe material we are discussing.
Returning to the subject of pressure testing and its objectives. One
of the key objectives of the testing is to find the possible flaws in
the constructed pipeline. The test develops a certain amount of stress
for a given time to allow these possible flaws to open out as leakages.
In the following section we shall discuss the relation of these flaws to
the test pressure and duration.
Critical Flaw Size
The maximum test pressure
should be so designed that it provides a sufficient gap between itself
and the operating pressure. In other worlds, the maximum test pressure
should be > MOP.
This also presupposes that after the test the surviving flaws in the
pipeline shall not grow when the line is placed in service at the
maintained operating pressure. For setting the maximum test pressure, it
is important to know the effect of pressure on defect growth during the
testing on the one hand and on the other flaws whose growth will be
affected by pressure over the time.
The defects that would not fail during a one-time, high test pressure
are often referred as sub-critical defects. However these sub-critical
defects would fail at lower pressure if held for longer time. But the
size of discontinuity that would be in the sub-critical group would
fail-independent of time-at about 105% of the “hold” pressure. This
implies that maximum test pressure would have to be set at 5-10% above
the maximum operating pressure (MOP) in order to find such defects
during the test and also to avoid growth of sub-critical discontinuities
after the hydro test pressure is released and during the operation life
of pipeline. This is should be the main objective of the hydro test.
If test pressure reaching 100% (design factor of 0.80) of the SMYS is
considered, then one must also consider some important pre conditions
attached to the procurement of the steel and pipe. Especially important
to consider is the level of flaw size that was accepted in the
plate/coil used to manufacture the pipe. The test pressure of such
magnitude would require that the acceptable defect size be re-assessed.
This is because all else being equal, a higher design factor, resulting
in a thinner wall, will lead to a reduction in the critical dimensions
of both surface and through-wall defects.
Where such conditions are likely it may be prudent to reconsider the
level of accepted flaws in the material. The current recommendations in
API 5L 44th edition for acceptance level B2 as per ISO 12094 (for SAW
pipes) may not be acceptable because it has limited coverage of body and
edges and the acceptance criteria is far too liberal, in terms of
acceptable size and area of flaws. More stringent criteria must be
specified more in line with EN 10160 where level S2 for body and level
E2 for edges may be more appropriate to meet the demands of the higher
test pressures.
Sub-critical surface flaw sizes at design factors of 0.80 and 0.72
are susceptible to growth at low stress and are time dependent. These
flaws are also dependent on the acceptable limits of impact absorbing
energy of the material and weld (not part of the discussion in this
article).
This increase in depth-to-thickness (d/t) ratio in effect reduces the
ligament of the adjoining defects that reduce the required stress to
propagate the discontinuity. Critical through-wall flaw lengths are also
factors to be assessed. While there is a modest reduction in critical
flaw length, it still indicates very acceptable flaw tolerance for any
practical depth and the reduction will have negligible influence in the
context of integrity management. Note that flaws deeper than about 70%
of wall thickness will fail as stable leaks in both cases. This
statement implies that mere radiography of the pipe welds (both field
and mill welds) may not suffice. Automatic ultrasonic testing (AUT) of
the welds will be better suited to properly determine the size of the
planer defects in the welds. Similarly the use of AUT for assessing the
flaws in the pipe body will be more stringent than usual.
Pressure Reversal
The phenomenon of pressure
reversal occurs when a defect survives a higher hydrostatic test
pressure but fails at a lower pressure in a subsequent repressurization.
One of the several factors that work to bring on this phenomenon is the
creep-like growth of sub-critical discontinuities over time and at
lower pressure. The reduction in the wall thickness, caused by
corrosion, external damages, is also responsible for a reduction in
puncture resistance in the pipe. The reduction in the wall thickness, in
effect reduces the discontinuity depth to the material thickness.
This increase in d/t ratio reduces the ligament between the adjoining
defects. This effectively reduces the stress required to propagate the
discontinuity. The other factor affecting the pressure reversal is the
damage to the Crack Tip Opening (CTO). The CTO is subject to some
compressive force leading the crack tip to force-close during the
initial test. On subsequent pressurization to significantly lower
pressure this “force-close” tip starts to open-up and facilitates the
growth of the crack. Hence, if such a pressure cycle is part of the
design, then the point of pressure reversal should be considered.
Puncture Resistance
- It may also be noted that there is a modest reduction in puncture resistance with both increasing SMYS and increasing design factor. Note that the maximum design factor is, in some instances, constrained by practical limits on D/t.
- In any event, it should be noted that only a small proportion of large excavators are capable of generating a puncture force exceeding 300 kN and that the reductions in puncture resistance noted would have to be assessed for the integrated approaches to the management of mechanical damage threats.
Source:
Komentar
Posting Komentar